It is common practice locally for contractors to take concrete and asphalt to one of the grinder facilities on the South Coast, have the materials ground up, and used as a recycled road base. The base is the sub-surface material, usually gravel and sand, that is compacted and becomes the surface on which the road asphalt is applied.
Thursday, October 2, 2008
Intersection Demo & Recycle
Wednesday, September 17, 2008
Phase 2 Begins: Big Changes Coming
We are now 6 weeks into construction and underground utility work is mainly complete. Although new and upgraded utilities and a new storm drain don't grab headlines, they are key to downtown Isla Vista becoming a focal point for the community.
During the next phase of construction we will begin to see the project really take shape with new sidewalk, street trees, lighting, bike racks and trash and recycling bins.
Construction during this phase will start near Giovanni's Pizza, El Sitio and 6-Pack Shop and move east toward campus. Contractors will spend about 1 month on each block with the project complete in December.
Please continue to visit downtown Isla Vista businesses during construction and show support for all your favorite restaurants.
Keep an eye on construction with the Pardall Webcam at: http://pardall.incipient.net/
The webcam is sponsored by Isla Vista business, Incipient Technologies. Find out more about what they do at: http://www.incipient.net/
The webcam is sponsored by Isla Vista business, Incipient Technologies. Find out more about what they do at: http://www.incipient.net/
Tuesday, September 9, 2008
60's Era Tiles Saved
Last week construction crews carefully removed handmade tiles made in Isla Vista during the 1960's by Hugh Carroll & John Greybill.
The Redevelopment Agency will be working with the IVRPD Board and community members on how the salvaged tiles can be reused as a public art feature along Pardall or in a public park.
Please visit IV Drip, Freebirds, Dublins, Steak & Hogie House and Pho during construction and show them your support.
The webcam is sponsored by Isla Vista business Incipient Technologies. Find out more about what they do at: http://www.incipient.net/
Thursday, August 28, 2008
Storm Drain
In a town where nearly everyone travels by foot or by bicycle poor drainage is just not acceptable. All day Wednesday and Thursday construction crews worked quickly to install the new storm drain that will control future flooding in downtown Isla Vista. The pipes seen here will connect to a new storm drain system and move rain water out of Isla Vista Streets. The manhole connects the Pardall pipe to the Embarcadero del Mar pipe.
Pardall Groundbreaking
Wednesday's groundbreaking event went off smoothly as construction crews too
k a break from installing the new storm drain at the corner of Pardall and Embarcadero del Mar. UCSB Chancellor Yang, First District Supervisor Salud Carbajal, Second District Supervisor Janet Wolf and about 50 others were on hand for the event to celebrate the first major project to go to construction from the Isla Vista Master Plan. Unfortunately, Third District Supervisor Brooks Firestone, whose office played an instrumental role in getting this project to construction was ill and could not attend the event.
Special thanks to UCSB, the Isla Vista Recreation and Parks District, the Isla Vista Foot Patrol, County Public Works, and all the students, residents and business owners who attended.
Silvergreens and FreshStart Cafe provided coffee and tasty snack.
To watch the video of the groundbreaking paste this link into your browser:
http://sbcounty.granicus.com/MediaPlayer.php?view_id=5&clip_id=626&publish_id=&event_id=
Special thanks to UCSB, the Isla Vista Recreation and Parks District, the Isla Vista Foot Patrol, County Public Works, and all the students, residents and business owners who attended.
Silvergreens and FreshStart Cafe provided coffee and tasty snack.
To watch the video of the groundbreaking paste this link into your browser:
http://sbcounty.granicus.com/MediaPlayer.php?view_id=5&clip_id=626&publish_id=&event_id=
Wednesday, August 20, 2008
Pardall Palms to Temporary Home
The palms will be temporarily stored on campus, west of the campus police station, near Mesa Rd and Stadium Rd. You can clearly see them from Mesa Rd as you pass by. They are being cared for by a professional arborist while at their temporary location. These types of palms,
Wednesday, August 13, 2008
Blue Pipe
Trenching and installation of the new water main is underway. Contractors are installing a new blue colored 8 inch water main down the middle of Pardall and backfilling the trench as they go. The contractors anticipating reaching all the way to the Embarcadero del Mar intersection by Friday.
The new water main also includes a new set of valves in the EDM intersection that will allow the water district to minimize downtown wide construction related water shut-downs in the future.